HL only This tool is for Higher Level students.
A project on a timeline: every activity as a bar, so managers can see what happens when, what can overlap, and where there is spare time.
Guiding question
How can a manager see at a glance whether a project is on track — and which delays actually matter?
Success criteria
- I can explain the features of a Gantt chart
- I can construct and interpret a Gantt chart from a list of activities, durations and dependencies (AO4)
- I can evaluate the Gantt chart as a project-planning tool
HL only
This tool is HL only (the guide lists it in bold). It is suggested for units 4 and 5 — for example, planning a marketing campaign or product launch (4.5) and production planning or R&D projects (5.6, 5.8). It pairs naturally with critical path analysis.
1. What it is and when to use it
Definition A Gantt chart is a project-planning chart that shows each activity as a horizontal bar against a timeline, so that the start date, duration, overlap and sequence of activities can be seen and progress monitored.
- Activities are listed down the side; time runs along the horizontal axis
- Each bar starts when the activity can begin (after its predecessors) and its length is the duration
- Activities with no spare time are critical; delaying them delays the whole project
- Other activities have float (spare time) and can be delayed within limits
- Shading the completed part of each bar shows progress against plan