Toolkit: Critical path analysis

Homearrow_rightBusiness Studies arrow_right Revision Notes arrow_right IBDP arrow_right Toolkit arrow_right Critical Path Analysis
IBDP Business Management · Change course

HL only This tool is for Higher Level students.

Finding the chain of activities that sets the shortest possible length of a project — and how much spare time every other activity has.

Guiding question
Which activities in a project can be delayed without consequence — and which cannot be delayed even by a day?

Success criteria

HL only
This tool is HL only. The guide states that it includes the completion and analysis of a critical path diagram (drawing the diagram is not expected), identification of the critical path, and calculation of free and total float. It is suggested for units 4 and 5 — product launches (4.5), production planning (5.6) and R&D projects (5.8).

1. What it is and when to use it
Definition Critical path analysis (CPA) is a project-planning technique that models a project as a network of activities, identifies the sequence of dependent activities that determines the minimum project duration (the critical path), and calculates how much each other activity can be delayed (its float).
Earliest start time (EST) of a node: the earliest time activities beginning there can start. Work forwards; where two activities meet, take the largest value.
Latest finish time (LFT) of a node: the latest time activities ending there can finish without delaying the project. Work backwards; where activities split, take the smallest value. Total float = LFT (end node) − duration − EST (start node): how long an activity can be delayed without delaying the project.
Free float = EST (end node) − duration − EST (start node): how long an activity can be delayed without delaying the next activity.

In this notation, each node is a circle divided into three parts: the node number on the left, the EST at top right and the LFT at bottom right. Activities are arrows labelled with a letter and a duration. Activities on the critical path have zero total float, and at their nodes EST = LFT.

🔒 Also in the full toolkit page
Join to unlock the full toolkit pageAlready a member? Log in
All toolkit tools← Contribution  |  Simple linear regression →